House Natural Resources Committee Issues Testimony From DOE Assistant Secretary Walker
"I appreciate the opportunity today to discuss the rebuilding and privatization of the
DOE Involvement in
"The
"In addition to the Department's role in emergency response,
"Over the course of the 2017 hurricane season, the Department deployed numerous personnel to support response efforts including: subject matter experts and technical advisors to
"
National Laboratory Modeling and Analysis
"The Argonne,
Real-Time Modeling Framework
"From the outset of our support for
Federal Interagency Coordination
"
"
Support for Energy Policy and Regulation
"The Southern States Energy Board (SSEB), in collaboration with
"
DOE Report on Energy Resilience Solutions for the Puerto Rico Grid
"
"On
Investment Considerations for
"Despite large Federal investments to date, the
"With its stakeholder partners,
"Total system costs could potentially fall through this single set of investments while at the same time enabling PREPA to catch up on deferred maintenance without raising rates. Moving to natural gas generation could also help bring PREPA into compliance with
"The near complete lack of industry-standard vegetation management greatly exacerbated damage to the transmission system during Hurricane Maria. While PREPA has awarded contracts for vegetation management in recent months, more must be done to protect local and Federal investment in the electrical system.
"Eighteen substations were significantly damaged by Hurricane Maria, and poor maintenance at many others leave the system susceptible to the potential failure of these critical components of the grid.
"Much of the high voltage transmission system repaired during the restoration process is fully functional as new, highly reliable assets. Targeted enhancements of the transmission system - especially along corridors identified as critical by the
"Incremental investments in advanced metering infrastructure, communications technology, smart grid devices, and grid monitoring and control systems would vastly improve the functioning of the distribution system - increasing reliability, reducing transmission line losses, and enhancing revenue collection.8
"Using sophisticated modeling techniques that combine grid infrastructure analysis with location of critical loads and interdependent infrastructure, the
"The single most important element regarding any new investments in
"Through mutual aid,
"Another key pillar of workforce development is professional and vocational training to develop a workforce pipeline at the robust systems engineering programs at the
"
"
Preparing for the Upcoming Hurricane Season
"The Incident Command System (ICS) is the industry-standard approach to emergency response that improves coordination and the cost-effectiveness of incident management. This structure was used by
Conclusion
"I am proud of the work
"Thank you, and I look forward to your questions."
* * *
Footnotes:
1
2
3
4
5 Investment Considerations for
6 Resolution and Order, In Re: Review of the Puerto Rico Electric Power Authority Integrated Resource Plan,
7
8
[TheHill]
Gov. Little approves Medicaid expansion restrictions
Everest Insurance Adds Industry Veteran Rick Taute as Vice President, Marketing & Distribution and National Wholesale Distribution Leader
Advisor News
Annuity News
Health/Employee Benefits News
Life Insurance News