Parkland prepares for $25 million in capital projects on horizon: renovations for Schnecksville Elementary, construction of fire-ravaged bus garage
The renovations to the
The first will be to renovate the southwest portion of the building, built in 1962, by adding new classrooms and replacing the school's heating, ventilation and air conditioning system. The work is slated to cost about
Most of the project is slated to be complete by the 2022-23 school year, with demolition wrapping up during the summer of 2023.
The Parkland bus garage near the
The districts transportation offices are currently housed at the Troxell building, but constructing them within the new bus garage will consolidate everyone in the department on site. Construction is slated to begin next year with an expected completion date early in 2021.
New debt for the work is expected to take the form of about
Morning Call reporter
___
(c)2019 The Morning Call (Allentown, Pa.)
Visit The Morning Call (Allentown, Pa.) at www.mcall.com