Parkland prepares for $25 million in capital projects on horizon: renovations for Schnecksville Elementary, construction of fire-ravaged bus garage
The renovations to the
The first will be to renovate the southwest portion of the building, built in 1962, by adding new classrooms and replacing the school's heating, ventilation and air conditioning system. The work is slated to cost about
Most of the project is slated to be complete by the 2022-23 school year, with demolition wrapping up during the summer of 2023.
The Parkland bus garage near the
The districts transportation offices are currently housed at the Troxell building, but constructing them within the new bus garage will consolidate everyone in the department on site. Construction is slated to begin next year with an expected completion date early in 2021.
New debt for the work is expected to take the form of about
Morning Call reporter
___
(c)2019 The Morning Call (Allentown, Pa.)
Visit The Morning Call (Allentown, Pa.) at www.mcall.com
Distributed by Tribune Content Agency, LLC.


Metro Transit union approves new contract after months of negotiation
Advisor News
- Benefit Costs Squeeze Schools, Driving Cuts, Tax Hikes And Difficult Tradeoffs
- Why client insurance needs could change even if their life doesn’t
- Most Gen Z investors think less than a year ahead when making financial decisions
- IRI pitches retirement agenda to Jeffries as democrats shape affordability platform
- Help child-free clients plan for their later years
More Advisor NewsAnnuity News
- Guidance, bulletin or reg? NAIC debates form of annuity illustration update
- Nationwide adds mutual fund-linked strategy to New Heights Select FIA
- NUNN INTRODUCES BILL TO CUT RED TAPE, GIVE IOWANS CLEARER INSURANCE INFORMATION
- NAIC working group pressed to accelerate annuity illustration overhaul
- State Auditor James Brown Kicks Off Life Insurance Awareness Month With Policy Locator Tool
More Annuity NewsHealth/Employee Benefits News
Life Insurance News