New contractor to finish replacing Colorado Springs Airport roof after blaze
A new contractor will finish replacing
It's unclear if the original roofer,
The late-night fire brought flights to a standstill and forced The Bristol Taproom and
Good summer forecast for
"Until that report is out, it would be improper and unfair to make conjecture," Phillips said.
The contractor began work in
"We just need to have them (
A new contractor has not been selected, but Phillips said he hopes the roof will be fixed "within the next couple of months."
Fire repairs are expected to be completed by
A request for proposals will be sent out in June for a general contractor for the reconstruction of the first and second floors, the report says. Construction of the second-floor public areas is scheduled to begin in July.
The insurance company already has given the airport a
"No matter who - if anybody - is at fault, it's still an insurance claim," he said.
-
Contact
Twitter: @lemarie
Credit: