N.Y. PSC Issues Order Involving Electric Emergency Response Plan Review
In the Matter of
ORDER APPROVING, SUBJECT TO MODIFICATIONS, THE AMENDED ELECTRIC EMERGENCY RESPONSE PLANS
BY THE COMMISSION:
INTRODUCTION
Each Investor-owned electric utility under the Commission's jurisdiction is required to develop, update, and file with the Commission a detailed Emergency Response Plan (ERP), detailing the utility's response plans for emergencies that comply with Section 66 of the Public Service Law (PSL) and Title 16 New York Code, Rules, and Regulations (NYCRR) Part 105./1
The electric utility's ERPs contain essential processes and procedures necessary to engage and respond to a wide array of emergencies. External and internal communication practices, personnel roles and responsibilities, and procedures implemented before, during, and following emergencies, represent just a fraction of the numerous measures that are required to be in each electric utility's ERP.
This year's review of utility ERPs reflects the actions taken following Tropical Storm Isaias, including outcomes from the notice of apparent violations and immediate corrective action letters sent to
The ERPs also incorporate findings from the Interim Investigation Report on Tropical Storm Isaias (Report) issued on
Many of the improvements made to the emergency response plans discussed in this Order relate to preventing inadequate storm responses, such as that of
The Commission, pursuant to PSL Sec.66(21), has a statutory obligation to review each investor-owned electric utility's emergency plans annually and 16 NYCRR Sec.105.5 also requires annual review and approval of emergency plans which are designed to ensure improved preparedness for future outage events. PSL Sec.66(21) requires all electric ERPs to be updated annually and submitted to the Commission for approval on, or before,
BACKGROUND
On
The 16 NYCRR Part 105 storm reports filed by each utility, as required by the Department's regulations, identified approximate peak outages of 380,000/6 for PSEG LI, 290,000 for
Approximately 90 percent of customers in the PSEG LI service territory were restored on
As a result of the extended restoration, each utility was directed in the Corrective Action Letters to undertake immediate action to add crewing capacity via retainer contracts as well as develop plans to secure utility crews in addition to private contractor and mutual assistance beyond the
NOTICE OF PROPOSED RULE MAKING
Pursuant to the State Administrative Procedure Act (SAPA) Sec.202(1), a Notice of Proposed Rulemaking was published in the
DISCUSSION
A thorough review was performed for each of the utility's electric emergency response plans filed in
Resource Acquisition and Mutual Assistance
The ability to effectively restore power in a timely manner after any storm event depends on how quickly electric infrastructure such as poles and wires can be repaired. The time it takes to repair electric infrastructure is dependent on the number of internal and external line resources a utility has available. When an electric utility has service outages resulting from a minor storm event, it normally relies on its own resources, such as internal line workers and on-property contractors to restore service. During larger storm events, the utility typically will secure third party contractors that supply line workers and restoration equipment or other skilled workers such as tree crews and damage assessors. The standard method to track and report resources is Full-Time Equivalents, or FTEs.
When a utility's total internal resources and on-property contractor resources are not expected to or do not meet the estimated resources needed to restore service, the utility will then contact external contractor resources and request resources through the
Estimated
The Estimated Time of Restoration (ETR) is the approximate date and time when the utility expects service will be restored after a power outage. Customers depend on ETRs to make health and safety decisions, including the need for alternative accommodations. Therefore, ETRs must be timely, accurate, and widely accessible. In
Last year, ETR Protocols were revised and strengthened based on recommendations from the 2018 Winter and Spring Storm Report./9
To balance the customer's need for information with available damage information and available crews, regional and local ETRs apply to 95 percent of customers instead of 90 percent. During Tropical Storm Isaias, customers and government officials were misinformed as a result of inaccurate ETRs, untimely issuance of revised ETRs, or the lack of clarity on who was covered by the ETR. As a result, customers and public officials were frustrated by the inaccurate, inconsistent, and insufficient messaging.
The ETR Protocols clearly outline extended time requirements for issuing local ETRs to enable utilities to provide more detailed and targeted information. All of the plans now identify individuals responsible for developing, issuing, and revising ETRs. It is imperative that utilities utilize all means of communication to inform the customers and government officials of ETR changes, including proactively reaching out to customers affected by changes and modifying their websites.
Coordinating with Counties and Municipalities
Following major storms, counties, municipalities, and utilities have a make-safe period that focuses on the elimination of hazards to the public. Public hazards include exposure to potential shock risks, which are hazards that can trap residents in their homes and can prevent emergency resources from responding to requests for assistance or fires. Strong and collaborative communications are critical when coordinating these efforts to develop daily work plans.
Additionally, regional municipal calls provide a venue for more detailed discussion of the municipalities' priorities and the presentation of updated information to the municipalities that is not available publicly. There have also been improvements in how utilities and municipalities interact, such as using virtual communications and through the use of municipal dashboards where municipalities can go online to report hazardous conditions, outages, blocked roads, and to track outages in their areas.
This information can also be obtained through utility liaisons, who may be co-located in municipal command centers, county EOCs or available around the clock to the municipalities by telephone. The utilities, however, need to understand that liaisons are only as good as the information that is provided to them. The ERPs contain language that acknowledges municipalities expect their liaisons to do more than reiterate publicly available information, e.g., locations and number of crews, which circuits are being worked, and the ETR status of their residents and/or constituents. Lastly, the ERPs include additional language for the utilities to request input from the counties in their service territories on dry ice distribution locations, however if counties are unresponsive, the utilities will still take action to ensure that customers get dry ice and will endeavor to accommodate reasonable requests to strategically locate distribution sites based on customer impacts.
Testing Critical Information Technology Systems
Customer reported outages are key to identifying the full impact of a storm event on an electric system after a major outage event. Therefore, outage reports from multiple sources, including the call center, Interactive Voice Response (IVR), utility website, and text messaging, are electronically posted to outage management systems (OMS) which are core applications used by utilities to manage outage events. OMS systems process reported customer outage information received through various means, predict outages to capture the full extent of customers impacted, create, prioritize, and manage jobs, and interface with various applications to provide consistent and updated outage information to utility personnel and the public during normal and emergency operations.
Two months prior to Tropical Storm Isaias, PSEG LI had gone into production with an updated version of its OMS without adequately performing realistic stress testing on the new version. Shortly after Tropical Storm Isaias hit its service territory, various failures in the OMS were identified, causing significant challenges not only for the utility but, more importantly, for the public. PSEG LI's OMS suffered a catastrophic failure that led to the Company's inability to provide accurate outage and job numbers, locations of reported outages, ETR information, as well as efficient and effective dispatching of resources.
As a result of the issues experienced by PSEG LI, each electric utility was required to stress test its respective OMS systems more frequently using more stringent parameters including, as part of the corrective actions following Tropical Storm Isaias, an outage impacting 90% or more of customers in the Company's service territory over a 24-hour period. These conditions will ensure the testing is in line with a realistic outage event and that the OMS will perform adequately in a major outage event.
To ensure this practice continues, the ERPs now include provisions that require OMS testing under the parameters listed above. The tests will be performed semi-annually with the detailed results provided to the Director of the
Additionally, if a utility OMS system fails a test, the utility is required to retest, after taking corrective actions, to ensure that the failure is corrected. A failed test does not count towards the semi-annual requirement. Each electric utility ERP also identifies how Advanced Metering Infrastructure (AMI) data will be used to improve the accuracy of its OMS. It is expected that additional automated processes will continue to be developed and integrated to improve storm response as AMI continues to be deployed by the utilities.
Information Technology
The utilities' websites, and any event-specific information pages, are two of the primary means used by utilities to inform customers during emergencies. When reviewing the many communication channels used to provide information to customers, e.g., press releases, social media posts, Interactive Voice Response (IVR) messages, etc., the utilities routinely direct customers to go to their website to gather more information. Therefore, the ERPs contain language that the utility website is required to be available around the clock. During storms, the information on the utilities' outage maps must be updated continuously at the typical cycle (e.g., every 15 minutes) and must be updated at least hourly, so to provide customers with information that is timely and accurate. If critical repairs and/or maintenance must be done, such activities will occur after
We cannot stress enough the need for critical systems to be operating properly at all times. Therefore, the Commission finds that it is imperative that as soon as a utility website or underlying data sources go down, it reasonable to require that the utilities notify on-call IT personnel expeditiously and without delay. IT personnel will work to resolve the issue and will provide updates on corrective action regularly and/or notify third party vendors in addition to facilitating any interactions between the vendors the utility's IT group.
When customer facing applications are experiencing a technical issue, the ERPs indicate the title of the employee responsible for directing that such notice be posted, e.g., message banner, on the main website homepage and the outage map, as appropriate, providing customers the details and necessary steps for reporting outages and obtaining other event-related information. This notice will also be used to communicate if system maintenance is underway and, if so, provide status updates on such as well as if the outage map is unavailable due to other issues, such as data quality concerns. The notices must provide outage counts and ETRs. In addition, the electric utilities also use social media to inform customers when these issues exist.
Furthermore, the ERPs designate the title of the employee responsible for stricter monitoring and maintenance of critical systems to ensure continuous access to the important information contained in those systems. These enhanced measures provide the utilities higher visibility and responsibility for making certain the critical information technology systems are properly maintained, but more importantly, diligently monitored so to identify issues quickly and be in a better position to ameliorate those issues effectively.
* * *
Footnotes:
1/ The investor-owned electric utilities are
2/ Case 20-E-0586, supra, Notice of Apparent Violation Related to Tropical Storm Isaias and Direction of Prompt Remedial Action (filed
3/ Tropical Storm Isaias struck on
4/ The PSEG LI ERP review followed a parallel process to the IOUs under Matter 20-02608, In the Matter of the
5/ The damage in
6/ The accuracy of this figure cannot be verified due to the issues PSEG LI had with its OMS.
7/ See, Matter 20-01633, In the Matter of DPS Investigation into the Utilities Preparation and Response to
8/ Case 13-E-0198, In the Matter of 2013 Electric Emergency Response Plan Review, Order Approving Electric Emergency Plans (issued
9/ Case 19-M-0285, In the Matter of Utility Preparation and Response to Power Outages During the
* * *
View full order at http://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId={C911E976-7617-4D3F-8259-012E4163E596}



CT utility regulators uphold millions in fines against Eversource, UI
After Riot Pause, Firms Resume GOP Donations
Advisor News
- Temporary tax hike to fill Medicaid gap heads to governor
- Iowa Senate sends health insurer tax increase to governor’s desk
- Temporary tax hike to fill Iowa Medicaid gap heads to governor’s desk
- Iowa Medicaid temporary tax plan draws sharp public opposition
- EDITORIAL: Make responsible tax cuts, increases
More Advisor NewsAnnuity News
- Corebridge, Equitable merge to create potential new annuity sales king
- LIMRA: Final retail annuity sales total $464.1 billion in 2025
- How annuities can enhance retirement income for post-pension clients
- We can help find a loved one’s life insurance policy
- 2025: A record-breaking year for annuity sales via banks and BDs
More Annuity NewsHealth/Employee Benefits News
- Health care costs in Colorado will grow under federal policy, patient advocates say; Sen. Hickenlooper says measure to require price transparency will help balance market
- Aflac adds new long-term care rider
- Inside Medicare Advantage ‘dark money’ group’s campaign to win bigger payments to insurers
- Brokers expect voluntary benefit sales to rise
- Federal Medicaid cuts could exact a heavy toll on psychiatric units at hospitals across the country
More Health/Employee Benefits NewsLife Insurance News
- AM Best Removes from Under Review with Positive Implications and Affirms Credit Ratings of Sompo Seguros Mexico S.A. de C.V.
- Corebridge, Equitable merge to create potential new annuity sales king
- Aflac adds new long-term care rider
- AM Best Affirms Credit Ratings of Nan Shan General Insurance Co., Ltd.
- Corebridge Financial and Equitable Holdings Announce Transformational Merger
More Life Insurance News