Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds
The rule was issued by
DATES: Effective:
FOR FURTHER INFORMATION CONTACT: Mr.
* * *
The adjustment uses the Consumer Price Index for all urban consumers, and does not apply to the Construction Wage Rate Requirements statute (Davis-Bacon Act), Service Contract Labor Standards statute, and trade agreements thresholds.
SUPPLEMENTARY INFORMATION:
I. Background
The preamble to the proposed rule contained detailed explanations of--
* What an acquisition-related threshold is;
* What acquisition-related thresholds are not subject to escalation adjustment under this case;
* How the
* The effect of this rule on the most heavily used thresholds.
FAR Case 2018-004, published as a final rule on
FAR Case 2018-005, published as a final rule on
FAR Case 2018-007, published as a final rule on
The following list identifies the impact of this rule on heavily-used thresholds.
* The micro-purchase threshold at FAR 2.101 was raised to
* The simplified acquisition threshold was changed to
* The preaward and post-award notices (FAR part 5) remain at
* The requirements for limiting competition (FAR part 6) to eligible 8(a) awards over
* The simplified procedures for certain commercial items ceiling (FAR 13.500) is increased from
* The cost or pricing data threshold (FAR 15.403-4) was increased by statute from
* The prime contractor subcontracting plan (FAR 19.702) threshold is increasing from
* The threshold for reporting first-tier subcontract information including executive compensation will not change (FAR subpart 4.14 and 52.204-10).
This is the fourth review of FAR acquisition-related thresholds since the statute was passed on
Seven respondents submitted comments on the proposed rule.
II. Discussion and Analysis
A. Summary of Significant Changes
Minor edits were made to the final rule to account for baseline updates caused by publication of other FAR interim or final rules.
The proposed rule included some thresholds that were very close but, ultimately, did not reach the statutory calculation formula amount. As a result, the Councils have removed them from the text of the final rule: FAR 9.405-2, 9.409, 13.402,
Some thresholds were inadvertently omitted, but are now included because they did reach the statutory calculation formula amount: 16.503(d), 19.804-6, 19.1506, 52.209-12, 52.222-50, and 52.222-56.
The FAR text also makes a correction to 52.222-50(i)(1). The paragraphs marked as (A) and (B) have been corrected to (i) and (ii), respectively.
B. Analysis of Public Comments
A discussion of the comments is provided as follows:
Comment: A respondent stated that there appeared to be an error in the proposed rule with a reference to FAR 42.709-0, as the current FAR has no 42.709-0; and did we mean the reference to 42.709-6 to be 42.709-7.
Response: The proposed rule contained the correct section numbering for sections 42.709-0 through 42.709-6. The Acquisition.Gov website reflected incorrect references, however, the Electronic Code of Federal Regulations reflected the correct FAR text.
Comment: A respondent asked why FAR 19.804-6 and 19.1506 did not appear in the proposed rule.
Response: These were inadvertently omitted. The required statutory changes now appear in the final rule.
Comment: A respondent stated it is unclear why the existing thresholds at FAR 19.1406(a)(2)(i) and 19.1506(c)(1)(i) are different than those established under FAR 19.805-1. The respondent stated that prior to 2006, FAR 19.805-1, 19.1306, and 19.1406 appear to have been identical (or similar) and one would assume that if these thresholds were adjusted based on the CPI, they would remain the same.
Response: The thresholds at FAR 19.1406(a)(2)(i), 19.1506(c)(1)(i), and 19.805-1 were established by different statutes. The calculations are set by 41 U.S.C. 1908, and are based on the enactment date of the underlying statute. The calculation for FAR 19.1406(a)(2) is based on a statute enacted
Comment: A respondent recommended that the Miller Act threshold be raised to
Response: There is no statute allowing this.
Comment: Two respondents stated that the
Response: These thresholds are not increasing in the final rule because they did not reach the statutory calculation formula amount (see Section II.A. of this preamble). In regard to whether bond thresholds are considered acquisition-related thresholds, the Councils disagree with the commenter's assertion that the thresholds are "required levels of insurance". The application of payment bond requirements are specific to a particular contract, however required levels of insurance apply more generally to a particular contractor. An example of a required level of insurance can be found at FAR 28.307-2, such as worker's compensation insurance which is required at
Comment: A respondent expressed general support for the rule.
Response: The support is noted.
III. Applicability to Contracts at or Below the Simplified Acquisition Threshold (SAT) and for Commercial Items, Including Commercially Available Off-the-Shelf (COTS) Items
This final rule does not create any new provisions or clauses, nor does it change the applicability or burden of any existing provisions or clauses included in solicitations and contracts valued at or below the SAT, or for commercial items, including COTS items, except for the changes in the thresholds themselves.
IV. Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated
V. Executive Order 13771
The rule is not subject to E.O. 13771, because this rule is not a significant regulatory action under E.O. 12866.
VI. Regulatory Flexibility Act
This final rule amends the Federal Acquisition Regulation to implement 41 U.S.C. 1908 and to amend other acquisition-related dollar thresholds that are based on policy rather than statute in order to adjust for the changing value of the dollar. 41 U.S.C. 1908 requires adjustment every five years of statutory acquisition-related dollar thresholds, except for Construction Wage Rate Requirements statute (Davis-Bacon Act), Service Contract Labor Standards statute, and trade agreements thresholds. While reviewing all statutory acquisition-related thresholds, this case presented an opportunity to also review all nonstatutory acquisition-related thresholds in the FAR that are based on policy. The objective of the case is to maintain the status quo, by adjusting acquisition-related thresholds for inflation.
There were no significant issues raised by the public in response to the initial regulatory flexibility analysis.
One threshold change in this rule which may impact small business concerns is the increase of the threshold for requiring a justification or determination for sole source 8(a) awards made pursuant to FAR 6.303-1 from
This rule does not include any new reporting, recordkeeping, or other compliance requirements on any small entities.
There are no known significant alternative approaches to the rule that would meet the stated objectives of the applicable statute.
Interested parties may obtain a copy of the FRFA from the Regulatory Secretariat Division. The Regulatory Secretariat Division has submitted a copy of the FRFA to the Chief Counsel for Advocacy of the
VII. Paperwork Reduction Act
The Paperwork Reduction Act (44 U.S.C. chapter 35) does apply; however, these changes to the FAR do not impose additional information collection requirements to the paperwork burden previously approved under OMB Control numbers: 9000-0006, 9000-0007, 1250-0004, and 1293-0005.
List of Subjects in 48 CFR Parts 1, 2, 3, 5, 6, 8, 9, 10, 12, 13, 15, 16, 17, 19, 22, 26, 32, 36, 42, 50, 52, and 53
* Government Procurement
Director,
[FR Doc. 2020-21690 Filed 10-1-20;
BILLING CODE 6820-EP-P
The document is published in the
TARGETED NEWS SERVICE (founded 2004) features non-partisan 'edited journalism' news briefs and information for news organizations, public policy groups and individuals; as well as 'gathered' public policy information, including news releases, reports, speeches. For more information contact



EDITORIAL: The Gazette's endorsements for Iowa's 2020 U.S. House and Senate races
Advisor News
- D.C. Digest: 'One Big Beautiful Bill' rebranded 'Working Families Tax Cut'
- OBBBA and New Year’s resolutions
- Do strong financial habits lead to better health?
- Winona County approves 11% tax levy increase
- Top firmsâ 2026 market forecasts every financial advisor should know
More Advisor NewsAnnuity News
- Judge denies new trial for Jeffrey Cutter on Advisors Act violation
- Great-West Life & Annuity Insurance Company Trademark Application for âEMPOWER BENEFIT CONSULTING SERVICESâ Filed: Great-West Life & Annuity Insurance Company
- 2025 Top 5 Annuity Stories: Lawsuits, layoffs and Brighthouse sale rumors
- An Application for the Trademark âDYNAMIC RETIREMENT MANAGERâ Has Been Filed by Great-West Life & Annuity Insurance Company: Great-West Life & Annuity Insurance Company
- Product understanding will drive the future of insurance
More Annuity NewsHealth/Employee Benefits News
- âEgregiousâ: Idaho insurer says planned hospitalâs practices could drive up costs
- D.C. DIGEST
- Medicaid agencies stepping up outreach
- D.C. Digest: 'One Big Beautiful Bill' rebranded 'Working Families Tax Cut'
- State employees got insurance without premiums
More Health/Employee Benefits NewsLife Insurance News