Six Sigma, the cloud and clarity
| By Bhar, Chandan | |
| Proquest LLC |
Project risk management makes installing electrical transmission lines in
Project risk management is an emerging domain in projects that install electrical transmission lines in
In developing countries, the problems can increase because the highly techni- cal projects take place in an infrastructure environment that is evolving, not mature. And in the growing economy that is
Each installation project involves simi- lar activities, but the technical details can vary to a large extent. And in
A risky business
Executives working in this sector have divided the whole process of electrical transmission line installation projects into various subsections. A quick analysis of one project helps us understand why.
In northern
In one such incident when a national level transmission line was being installed, a few sections of the line were delayed so much that the critical path (the sum of the total time taken to complete all the proj- ect's essential activities) almost doubled what was planned. So professionals always spend a large amount of time dividing the project into various subsections to try to reduce critical path time and make risk management more effective.
Our study surveyed professionals to come up with a common description for these subdivisions of activities necessary to complete the installation of any conven- tional electrical transmission line. The main divisions are:
1. Tower base preparation
2. Construction of tower
3. Installation of ground wires
4. Erection of electrodes and conductor
5. Stringing, sagging and clipping
6. Installation of associated hardware
7. Jumper cable installation
<p>8. Vibration damper installation
9. Spacer installation
Each of these common processes can be termed a phase in the installation of any transmission line, irrespective of its length and working voltage. It is worth mention- ing that for a 33,000-volt line that covers more than 500 kilometers, contractors could start work in more than 25 sites along the whole stretch of the line. In many projects, work starts simultaneously on many different sites. Giving contracts to different players over a large geographic region helps reduce the project's critical path time by initiating a large number of parallel activities.
However, this also makes it diffi- cult to monitor risk, and the industry faces many losses. The need for central monitoring is great, but the numerous small contractors involved don't always follow standard guide- lines. This increases each project's risk, sometimes leading to a drastic blow for project outcomes through delays - or even completely halting a section of the project.
As you can see, ensuring that work on different sections of the line constantly adheres to guidelines for proper risk mitigation is a major problem. Personal experience, combined with discussions from experts in this field, shows that most monitoring is done in the form of sheets that list different parameters, and each site can have multiple sheets detailing the tower's parameters.
These sheets are used to monitor work progress and measure the project's tech- nical attributes. Safety guidelines, which are filled out on a regular interval in every project and subsection, also are included. However, applying a
Suggested methodology
Still, experts in the field had some apprehension when discussing whether
According to Total Quality Manage- ment by
After much discussion with experts in the field, the team approved the methodol- ogy. That left the team with the large task of making the plans work on actual projects.
Automating inspection
Automating inspection sheets and compil- ing them on a central server requires an arrangement that collects data on a daily basis. Smaller projects can have teams dedicated for automating inspection on a weekly or daily basis for each segment of the project.
But on larger projects, the process must be fully or partially automated because of the risk level and monetary inputs. There- fore, we suggest that larger projects follow a system for automatic collection of risk- related inspection data sheets.
The inspection sheets must be devel- oped before the company starts installing any electrical transmission lines. These sheets can cover the projects' various divi- sions and risks and include checking the poles, making sure the transmission lines don't sag, and scheduling line checks.
Figure 2 shows a sample inspection sheet from a leading company that installs transmission lines, while Figure 3 shows the division of a conventional trans- mission line and its cost breakup. The division comes from
Since implementing
1. Develop software that can process the daily inspection lists for precautions in an electrical transmission line project.
2. The main functionality comes from collecting this inspection data from a project that sometimes can span more than 500 kilometers. The much-talked- about phenomenon of cloud computing, used by many leading companies like
3. In the next step, data from each construc- tion site will be collected and sent to the central risk command center.
4. This command center processes the data and applies a proper risk mitiga- tion plan for each site. This is a drastic improvement over the present system, where common risk mitigation plans are applied at all sites.
Figure 4 summarizes the whole process.
System validation result and future research
As a part of the initiative, we incorporated a risk command center at a small level in a project to install an 11,000-volt transmis- sion line.
The data was collected through daily inspections and sent to the central command via organizational email iden- tifications given to the contractor for the small project.
In the case of larger projects, cloud computing can use a separate local area network (LAN) to handle the emailed traffic. Many companies have developed interactive information sharing systems with cloud computing-enabled nodes for various project works. In our case, large transmission line projects follow this system to send data back to the central risk command center.
The command center processes the data and prepares risk plans for that project. The project showed signs of performance improvement, as site supervisors and engineers faced fewer day-to-day operational difficulties. In fact, 82 percent of the respondents reported that the system reduced operational difficulties.
In prior projects, site supervisors said they had to handle an average of 10 to 12 delays or halts each day because of various risks. The supervisors would make changes to ameliorate the problems, and the proj- ects would continue. But introducing this system allowed supervisors to be proactive, giving better technical advice and reduc- ing delays to an average of seven or eight times a day. These results infer that the new system decreases the risk impact and increases risk mitigation capabilities.
Although the system seems to be performing well, validation needs to happen on real-time, large-scale projects that install electrical transmission lines over lengthier geographic areas. Just as impor- tantly, most site supervisors welcomed the new system. In addition, data collection on a larger scale, not to mention the ability of central servers to incorporate more data about past instances and risks, should help reduce risks on larger projects. This leads to the conclusion that the system should be highly adaptable and easily scaled up to larger projects.
On-site experiences and the accounts of managers who handle projects that install electrical transmission lines helped the team classify the various risk catego- ries involved, account for the impact these factors have on such projects, and find out what bothers the working profes- sional in the field. The results show that constant ignorance of risk management has drastically negative results on project performance.
But the
Many experts in this field strongly advocate having a governing body for risk management because, they say, after proj- ects are tendered, most contractors pay limited attention to risk management on site. While most contractors follow the rules on paper, in practice, due to either ignorance or their desire to increase profits, they consider risk mitigation plans unnec- essary and do not follow them.
But when these risks explode into real problems, the results often jeopardize the entire project by increasing the criti- cal path time necessary to complete the installation, not to mention the safety concerns for workers and the question of whether the project meets technical spec- ifications. Only then does the contractor realize the importance of preparing for risks before they occur.
Introducing a
electrical nontransmission
During 2008 to 2009, the nation lost 28.44 percent of its electricity during transmission and distribution. Electricity shortages cause numerous power outages throughout
Despite an ambitious rural electrifcation program, some 400 million Indians lose electricity access during blackouts. While 84.9 percent of Indian villages have at least one electricity line, just 46 percent of rural households have access to electricity, the website reported.
| Copyright: | (c) 2014 Institute of Industrial Engineers-Publisher |
| Wordcount: | 2426 |



The pros and cons of ISO
Advisor News
- Why timing the market is still a retirement mistake and what to do instead
- Business owners may be overlooking a key part of their financial picture
- How smart investments prepare clients for inflation
- Amid slew of corporate tax ideas, Newsom chose one likely to hit people’s premiums
- The biggest risk to your clients’ financial plans isn’t market volatility
More Advisor NewsAnnuity News
- Best’s Special Report: U.S. Life/Annuity Industry Sees Bottom-Line Growth Despite 18% Decline in Total Income in First-Quarter 2026
- Globe Life Inc. (NYSE: GL) Records 52-Week High Thursday Morning
- Fortitude Re Completes $500 Million FABN Issuance
- Reframing retirement income for greater certainty
- Jackson Introduces Dow Jones Industrial Average Index Option, Flexible Premiums, Six-Year Rate Guarantee in Latest Registered Index-Linked Annuity Launch
More Annuity NewsHealth/Employee Benefits News
- OC supervisors would be removed from CalOptima board under California bill
- Centene offers employee buyouts as insurance rolls shrink
- Studies from University of Illinois Chicago in the Area of Chronic Kidney Disease Described (Hyperkalemia and its treatment: real-world evidence and managed care considerations supporting use of potassium binders): Kidney Diseases and Conditions – Chronic Kidney Disease
- New Findings Reported from American Dental Association Describe Advances in Managed Care (Medicare Advantage Dental Benefits: Comprehensive Coverage Available In Fewer Than Half Of US Counties): Managed Care
- REPORT: 2M Illinoisans face $500 cut as Social Security faces cliff
More Health/Employee Benefits NewsLife Insurance News
- An Application for the Trademark “LIFE INSURANCE THAT ENHANCES LIFE” Has Been Filed by Pacific Life Insurance Company: Pacific Life Insurance Company
- AM Best Assigns Issue Credit Rating to Sammons Financial Group, Inc.’s New Senior Unsecured Notes
- How much money do Connecticut residents need to retire comfortably?
- Advocates: Life insurers potentially missing millions of deaths annually
- How much money do Connecticut residents need to retire comfortably?
More Life Insurance News