Merge With CAUTION
| By Alderton, Matt | |
| Proquest LLC |
Once the ink on the merger deal dries, the real work begins: uniting disparate projects and teams across the portfolio.
Merger and acquisition deals (M&As) may seem the domain of accountants and attorneys, but it's project leaders who help a new organization thrive by helping decide which legacy initiatives to keep and which to kill.
And it looks like there will be more post-merger portfolio transitions to contend with. Some 40 percent of executives told Deloitte in June they expect M&A activity to increase in the future. Likewise, M&A tracking company
For these deals to truly succeed, organizations must take a deep dive into the portfolio, assessing whether the new company has the right mix of projects. A project that might have been perfectly aligned to the strategic vision at one company may be redundant or out of sync with the new organization's goals.
"It is of the utmost importance to revisit projects at the portfolio level in order to determine their strategic relations and importance to both companies post-M&A," says
He offers an example of two companies with a shared customer. In each company, the customer may be considered a low priority because of its lesser spend relative to other customers. When the companies merge, however, a portfolio analysis shows the customer's combined spend with both entities now makes it a high priority. "This is a simple illustration of the benefits of looking at projects collectively as opposed to reviewing them in silos."
Here are four tips to ensure a happy marriage:
Establish Centralized Leadership
M&As don't just affect existing projects. They create new ones, says
"The merger itself will typically result in the launch of an enormous project. Both companies have an existing portfolio of projects that already have resources, timelines and budgets associated with them," he says. "Now, suddenly, this new post-merger integration project comes along and forces you to go back and question the relevance of those portfolios."
Once the deal is closed, organizations may want to consider forming an enterprise project management office (PMO) to lead the integration process.
To promote rapid and effective decision making, the PMO should have a clear line of sight to executive sponsors and should treat all lines of business objectively.
Most of all, however, it should be inclusive. "The only way it will succeed is if it's a joint team,"
Define Strategic Priorities
The first order of business is for the executive leadership to establish new strategic objectives-and then pick the projects that will help the new organization achieve them.
"You need to start with a strategy and establish the main goals to be achieved," says
PMP, IT manager for the Brazilian division of
When
Without that kind of clear direction from the executive suite, project teams can get lost.
"Project teams can get off track or have conflicting messages or resource-contention issues across the integration portfolio and not meet the tactical objectives," says
Take Inventory
With strategic objectives established, the integration team must identify projects currently underway at both legacy organizations.
"There needs to be an assessment done sooner rather than later of your entire portfolio,"
Initially, this inventory simply lists all projects underway and resources deployed. Once strategic priorities are set, however, organizations must take a deeper dive to make a call on which projects should be continued, canceled or deferred when the merged company rebalances its portfolio. Among the most important decision points:
* Strategic alignment: Projects that further the merged organization's goals should be continued, and those that don't should be Idled or postponed. When
* Project type: Some project categories should be considered mandatory. "Let's say there's a project that is intended to address a regulatory/compliance issue. You would probably proceed with that project because it's critical to the organization,"
But even compulsory projects should be scrutinized post-merger. "Challenge any dates established to confirm priority," advises
* Project timeline: A project's post-merger survival often hinges on time, including how far along the project is and how long it will be useful post-integration.
"If there was a project to design an application or solution with a useful life of eight to 10 years, and it was going to cost X amount of money,"
If the integration will take several years, a cost-benefit analysis might show it makes sense to proceed with projects that enhance the company's ability to do business in the near term, even if their long-term value is questionable.
* Project status: Troubled projects, especially those in their early phases, typically are prime candidates for cancellation, deferral or de-scoping. But not all nascent projects should be dismissed. "Projects that are tracking well should be looked at to make sure they can still track to dates given the integration work,"
(Re)AlIocate Resources
Of course, project portfolios aren't the only things that have to be rebalanced post-M&A Human resources must likewise be assessed against new strategic priorities, so HR practitioners should be brought into the post-merger integration as early as possible, says
"Integration is never easy, and very often what HR is left to deal with are issues related to low employee morale, frustration and job uncertainties," she says. Calling in HR as early as the due diligence phase can also help mitigate cultural differences and risks, Ms, Mathew adds.
In collaboration with the post-merger project leaders, HR professionals help determine the merged organization's needs and the legacy employees available to meet them, while also identifying gaps to fill and redundancies to eliminate.
"HR'vä®! seek to answer: Can we as an acquiring company absorb the acquired company's skill sets and expertise? Are there project resources that can fill our current gaps? Who are the key staff we want to retain?" says Ms. Mathew.
One of the best ways to answer these questions is to involve as many project professionals as possible from both legacy companies in the post-M&A project. "By having both sides involved in integration planning and execution, you can get a good feel for project management capabilities and skill sets,"
M&As inevitably set everyone on edge, so it pays for organizational leaders to be transparent "You need to make decisions and communicate those decisions in a very dear way to everyone,"
Making the Cut: How to Survive a Merger or Acquisition
Mergers and acquisitions are a business blood sport. Although organizations often emerge leaner and stronger, the same isn't always true of project managers and their team members, whose positions are sometimes casualties of post-merger integration. The following tips can help you survive-even if your job as you knew it doesn't:
* EMBRACE CHANCE. "Resistance is futile," says
* BE FLEXIBLE. Just because your job is eliminated during post-merger integration doesn't mean you will be. If you're open to relocation or reassignment, opportunities may exist elsewhere in the organization, according to
* BE PART OF THE DEAL. "Any opportunity a project manager has to get involved in the phases of a potential acquisition helps one continue to build business acumen, develop relationships and work closely with senior executives," says
"It Is of the utmost importance to revisit projects at the portfolio level in order to determine their strategic relations and importance to both companies post-M&A."
-
"Project teams can get off trade or have conflicting messages or resourcecontention issues across the integration portfolio and not meet the tactical objectives."
-
"If there was a project to design an application or solution with a useful life of eight to 10 years, and it was going to cost X amount of money, but, because of post-merger integration, now it might only have a two-year fife-is it still worth it?"
-
"Integration is never easy, and very often what HR is left to deal with are issues related to low employee morale, frustration and job uncertainties. Calling in HR as early as the due diligence phase can also help mitigate cultural differences and risks?'
-
| Copyright: | (c) 2013 Project Management Institute |
| Wordcount: | 1850 |



Policing the AGILE Expressway
Underwater Intervention 2014
Advisor News
- The modern advisor: Merging income, insurance, and investments
- Financial shocks, caregiving gaps and inflation pressures persist
- Americans unprepared for increased longevity
- More investors will seek comprehensive financial planning
- Midlife planning for women: why it matters and how advisors should adapt
More Advisor NewsAnnuity News
- LIMRA: Annuity sales notch 10th consecutive $100B+ quarter
- AIG to sell remaining shares in Corebridge Financial
- Corebridge Financial, Equitable Holdings post Q1 earnings as merger looms
- AM Best Assigns Credit Ratings to Calix Re Limited
- Transamerica introduces new RILA with optional income features
More Annuity NewsHealth/Employee Benefits News
- SENATE APPROVES BILL TO LIMIT PREMIUM INCREASES, PROTECT ACCESS TO HEALTHCARE
- All about AHCCCS: Navigating Arizona Medicaid’s changing landscape
- GOVERNOR SIGNS BIOMARKER TESTING COVERAGE BILL
- REGULATION OF AI IN PRIOR AUTHORIZATION AND CLAIMS REVIEW: A LOOK AT FEDERAL AND STATE CONSUMER PROTECTIONS
- LEADING HEALTH ORGANIZATIONS URGE NC LAWMAKERS TO RECONSIDER PROPOSAL IMPLEMENTING MEDICAID CUTS
More Health/Employee Benefits NewsLife Insurance News
- 2025 Insurance Abstracts
- AM Best Assigns Credit Ratings to Tokio Marine Newa Insurance Co., Ltd.
- Earnings roundup: Prudential works to save ‘unique’ Japanese market
- How life insurance became a living-benefits strategy
- Financial Focus : Keep your beneficiary choices up to date
More Life Insurance News