When the dam jams
| By Diane Dietz, The Register-Guard, Eugene, Ore. | |
| McClatchy-Tribune Information Services |
On
Dam operators that day were trying to deal with a pile of debris that had pressed against the dam's No. 2 roll gate.
In especially heavy rains, branches, leaves, roots and sometimes even whole trees are washed into the McKenzie from the
The rains were heavy that day. The
Dam operators were well aware of the problems that huge masses of tree debris could cause at the dam.
On the very same day the previous year --
When debris gathers against a
Three rolling-pin shaped "rollers" with concrete piers in between them are strung across the river, holding back
The system's design flaw, the
"You'd have to jockey (the gates)," he said. "Some people got really good at jockeying them."
In the
Crews had raised the gate up to 9 feet in the debris-flushing maneuver, but then something inexplicable happened.
Suddenly, the 90-ton gate was in free fall, and the water gushing under the dam was stopped.
The dam operator had to quickly raise gates No. 1 or No. 3, or both, to keep water moving through. It would have taken about two minutes to re-establish the flow, said
"You would have seen the water change its location (to the No. 1 and No. 3 spillways)," he said.
EWEB staff say the gate's collapse in and of itself wasn't a major calamity. But it remains stuck shut 24 months later, so the dam's ability to handle floodwater is diminished.
And the utility will need to spend about
"It just wasn't that big of a deal," EWEB spokesman
A second opinion
With roller gate No. 2 jammed, the dam's capacity to let water through is reduced by one-third, down to 66,000 cubic feet per second from 99,000 cubic feet per second.
Another storm, and another slug of branches and roots pressed against the other dam gates, could lead to a bigger problem, according to regulators.
"The hoisting mechanisms for the other two gates are the same type as the system that failed on gate No. 2 and therefore could potentially contain the same defects that resulted in that gate's failure," the regulator wrote to EWEB.
"A similar failure at either of the remaining gates could create a situation where the dam could no longer safely pass flood flows, and as shown by the failure of gate No. 2, the time required to return the gate operation could be significant."
EWEB Commissioner
"What would happen if another one of these (dam gates) fail next week? Then what would happen?" Brown said. "If roll gate No. 1 slams down and breaks, then we've got problems. ...
"If we all of a sudden dam that up, how quickly is it going to flood out all those houses -- and septic tanks (around the lake)?
"It would be a mess."
The two years since the hoist on gate No. 2 broke is demonstrating just how long it takes to get such a gate fixed, Brown added.
Latest and greatest
Roller dams, notwithstanding their debris problem, once were a pretty reliable way to hold back river water. They're powered by electric motors, which turn a sprocket and chain. One end of each roller has teeth that fit in the chain.
The rollers pivot as the chain draws them up through the wide grooves in the concrete piers. The three little houses on top of the piers shelter the engines and gearworks.
In the 1950s, EWEB installed stand-up wooden "flashboards" on top of each of the dam's three roller gates, which allowed the dam to hold back more water and raise the level of the lake by 21 inches.
Raising the lake means EWEB can divert more water into a power canal and through its turbines, so it could produce more electricity.
EWEB eventually learned that the 1950s lake level put too much stress on the roller gates. They were "significantly overstressed" and needed reinforcement, according to an engineering report.
In the early 2000s, EWEB again wanted to raise the lake, this time by 18 inches.
EWEB wanted to retain more water because regulators had required EWEB to put a fish screen in its power canal to keep salmon out of the turbines. The screen restricted the flow and reduced the velocity of water -- and creation of electricity -- by about 14 percent, EWEB told the
If EWEB raised the lake, it figured it could regain the lost velocity and power. The utility hired engineering firm Montgomery Watson Harza, later MWH, for advice.
MWH winnowed alternatives down to two:
Replace the three old electric motors and gears with a high-end hydraulic gate hoist system that could take the added pressure of a 1 { -foot lake rise.
Don't raise the lake level. Instead, replace the three aging electric motors and replace any gears that are worn out. Without the added pressure of a higher lake, the feeling was the system could continue on pretty much as it was.
In any case, the utility had to add
EWEB made its choice: It would raise the lake. It bought three hydraulic systems manufactured by a Swedish firm from a Scottish marine engineering company.
A hydraulic motor, MWH's report said, virtually would be maintenance free.
"Engineering said: 'Hey if you put this in, you won't have to interface with it as much,'" Kline said. "It's kind of the latest and greatest."
Yet, apparently, nobody had tried operating a roller gate dam with a hydraulic motor. It was a novel application that the salesman touted in a
EWEB installed the hydraulic motors in 2004 and raised the lake in 2005, but only by 6 inches. The utility decided against raising the lake the additional foot, in part because the plan had raised the ire of one or two dozen owners of expensive lakefront property.
In the end, the pressure on the dam was less than the engineers had prepared for.
Then came that stormy day in 2012. When the operator had the gate fully raised -- at 9 feet up -- he suddenly realized the hydraulic pressure indicator was at zero, according to EWEB documents.
Something had gone drastically wrong in the No. 2 pier house, inside the motor casing where the massive raising-and-lowering rotor normally spun.
The roughly 6-inch-thick iron wheel broke into more than 20 pieces.
EWEB still doesn't know why it broke, but it hired a new engineering consultant to find a fix. U.S.-based Mead & Hunt produced an engineering report in
The engineers found no other roller gate dam in the country had a hydraulic motor. The consensus at EWEB was that a new electric motor was the way to go.
"This style of system requires little maintenance, and most have been in operation for 50 to 75 years with little or no problems."
So, this summer, EWEB plans to go back to the future and install a new electric motor and gears for roller gate No. 2.
"We believe the chain and hoist mechanism is still the right way to accomplish this task," Kline said, "so that's what we're doing."
In hindsight, would it have been better if EWEB had stuck with the electric drive instead of choosing the so-called "latest and greatest" technology?
Kline's not saying: "I'm not going to negatively comment about those who went before me," he said.
No recovery expected
When a consumer buys a product and it fails before its expected lifespan, the buyer generally asks for a refund or a replacement.
That apparently seemed logical to elected EWEB Commissioners
"I hope we'd look to the manufacturer for some kind of compensation" Commissioner Brown said in an interview, "because if you have a 50-year life expectation and it lasts for seven, I'm sure we have some kind of recourse on them."
Kline confirmed that the motor didn't last as long as it was designed to.
"The standard (rule of thumb) is 20 years for any sort of rotating equipment or machinery. You would expect at least a 20-year life cycle out of it."
In 2012, EWEB hired a metallurgist to investigate what caused the rotor to shatter. But the metallurgist couldn't say definitively whether it was caused by the operation or by improper foundry practices when the rotor was cast.
"The most probable cause of this hydraulic motor failure is the defective rotor casting," he wrote in his report.
But EWEB has decided not to pursue a warranty claim, Kline said. The only warranty was a yearlong construction warranty, he said, long since expired.
In its defense, the manufacturer might point to other factors, including engineering reports in 2001 and 2013 that cast doubt on EWEB's maintenance practices.
In 2001, before the hydraulic motor was installed, the MWR report found that staff didn't keep maintenance records, lubrication was done regularly but not on a predetermined schedule, and the hoist chains hadn't been lubricated in several years.
The 2013 engineering report by Mead & Hunt found only one maintenance problem: "a regular chain lubrication regimen has not been carried out during the lifespan of the Gate 2 hoist system due to access constraints." But the consultant said the chain did not appear to be degraded.
"I would liken it more to maintenance records versus maintenance," Kline said.
"I'm confident that there was maintenance done to all the infrastructure that's in our care."
Operators since have upped their maintenance record keeping drastically, he added.
In any case, Kline said that EWEB had "no recourse" to collect from the Scottish hydraulic motor sales company or the Swedish manufacturer.
"(It's an) international manufacturer; it's been installed for north of eight years, and the cost of fighting would not equal the benefit of recovery," Kline said. "We had no indication, whichever way we looked at it, that there would be a path to recovering this investment."
Woulda, shoulda, coulda
Ironically, even as EWEB faces the
Today, the
If it were deciding today, EWEB might have left the lake level alone and maintained the electric gate hoist system.
"Right now," Kline said, "The future look of power is not the same as it was then. We would seek other alternatives most likely."
EWEB took out
In years since, the utility has earmarked roughly
Simultaneously, EWEB is struggling with relicensing the
Is it worth it?
"That's a big question," EWEB Commissioner Brown said. "We have to make a
Relicensing would require a
"We own the dam and we either relicense it or we decommission it. Right now were in limbo," Brown said. "I wouldn't be surprised if we didn't start talking about (decommissioning) -- I mean,
Harwood, however, said it's impossible to know what the future holds.
"If you look out 20 or 30 years, you see this glut of natural gas and that's what's depressed the wholesale market (for electricity).
"What happens in five or six years, again this is pure speculation, when the environmental regulators catch up with the people who are fracking?
"Now, all of a sudden, environmental regulation adds a whole layer of cost.
"All of a sudden, hydro and wind and other things are not only profitable again, but they're cheaper."
In 2001, EWEB couldn't have predicted what came down the pike.
Moving forward
EWEB had to fix the
Currents had scoured away the riverbed underneath the ladder, leaving it hanging unsupported. Crews placed giant bags under the ladder and pumped them full of about 60 cubic yards of concrete to restore the ladder's foundation.
"That was a much higher risk" than the roll gate, Kline said. "It had a much larger and more likely liability for failure."
Kline emphasized that
With one gate closed, the dam's capacity for draining a swollen
In the big flood of
"There was no dam, it was all
EWEB has been methodical and deliberate in figuring out how to restore roll gate No. 2, Kline said.
"Our focus is to try to do the right thing with the public's money, and if that means taking two years to replace the (hoist) by putting back the right (motor system) for the
___
(c)2014 The Register-Guard (Eugene, Ore.)
Visit The Register-Guard (Eugene, Ore.) at www.registerguard.com
Distributed by MCT Information Services
| Wordcount: | 2940 |



124 file for May Primaries
Advisor News
- Retirement optimism climbs, but emotion-driven investing threatens growth
- US economy to ride tax cut tailwind but faces risks
- Investor use of online brokerage accounts, new investment techniques rises
- How 831(b) plans can protect your practice from unexpected, uninsured costs
- Does a $1M make you rich? Many millionaires today don’t think so
More Advisor NewsAnnuity News
- Great-West Life & Annuity Insurance Company Trademark Application for “EMPOWER BENEFIT CONSULTING SERVICES” Filed: Great-West Life & Annuity Insurance Company
- 2025 Top 5 Annuity Stories: Lawsuits, layoffs and Brighthouse sale rumors
- An Application for the Trademark “DYNAMIC RETIREMENT MANAGER” Has Been Filed by Great-West Life & Annuity Insurance Company: Great-West Life & Annuity Insurance Company
- Product understanding will drive the future of insurance
- Prudential launches FlexGuard 2.0 RILA
More Annuity NewsHealth/Employee Benefits News
Life Insurance News
- To attract Gen Z, insurance must rewrite its story
- Baby On Board
- 2025 Top 5 Life Insurance Stories: IUL takes center stage as lawsuits pile up
- Private placement securities continue to be attractive to insurers
- Inszone Insurance Services Expands Benefits Department in Michigan with Acquisition of Voyage Benefits, LLC
More Life Insurance News