Lawsuit filed against construction company over downtown Marshall project
Building owners in downtown Marshall have filed an insurance claim and a lawsuit against
The project encompasses the 300 and 400 block of
Since the project began, building owner
Similarly, building and business owner
Casey Slone, owner of
According to City Public Works Director and Engineer
The first portion of the project encompassed the removal of the current sidewalk, beginning on the west side of the 300 block of North Washington and then moving to the east side of the street.
It was during the initial removal of the sidewalk that Slone's crew discovered an old, hand-laid brick stormwater pipe beneath the east side of the 300 block, and on both sides of the 400 block as well.
Powell and Slone said that this changed the scope of the work being done, and required new material estimates as well as a change order officially approved by the city council before work could continue in those areas.
During that time, between when work began the end of January and when the change order was approved by council on
It was this work with the removal of the sidewalk initially that Yohn said caused severe damage to the foundation of her building at 304 N. Washington, located on the east side of the street.
The lawsuit against the company claims that the work being done around the second week of February caused severe damage to the building's footer as well as to the building's support. The damage done to the building and the cost to have professionals out to appraise and fix the building will cost Yohn around
Yohn said that she had more than one interaction with both city officials and representatives of
"Downtown Marshall is very important to my family, and we want these buildings to last for generations to come. We support the sidewalk improvement project, but we also expect Casey Slone, as the city's hired contractor, to make these improvements with the utmost care to our historical properties. This has not been the case," Yohn said, "Property damage 'accidents' do happen, but accountability and integrity in handling these issues should have been the priority, not a continued denial of responsibility."
She said that the issues came to a head on
Both witnesses wrote in separate statements that Yohn asked Slone multiple times during the interaction if he would file an insurance claim to fix the issue, which Slone responded was not his problem, eventually telling Yohn to sue him and sue the city.
Slone denied the statement, referring to them as lies, and would not comment further on any interactions with Yohn.
That evening,
Yohn said she contacted attorney
The issue was brought to court on
"The buck stops with
Watts said that his issues began in February with the flooding of his building caused by a massive rain storm, with mud and debris filling his finished basement which he said came from the large hole in the sidewalk made by construction work, which he referred to as negligent.
Watts contacted Powell at the time of the incident through email, setting up a meeting with the engineer for an in-person conversation, with Powell more recently stating he did not recall the issues surrounding the flooding of Watts' property in February.
However, Watts said he immediately notified
Watts later noted
Watts said that placement of sandbags and the creation of his own waterproofing successfully halted the flooding he saw in February, including during the more severe massive rainstorm experienced on
Slone said he was not made aware of the flooding incident at the time or presently. Both Powell and Slone stated that unfortunately, with construction work, water will flow to the lowest point, and that the team and the city cannot control the weather and would themselves, prefer clear, sunny days to continue to get work done.
"At the time I really did not want to make a fuss, I know how projects like this work and I know stuff like this can happen, so if the flooding was the only issue I would have probably left it alone," Watts said. "They put you in a corner, no one wants to make waves, but the situation continues to happen."
However, when work on the west side of the block kicked back up after the change order was approved in
Watt's building at 303 N. Washington houses not only a ground-floor business, but three tenants upstairs at the property. He said that the broken sewer line caused all water draining from the upstairs tenants to flood into the downstairs toilet and into the lobby, causing a mess of sewage and water to flood into the building.
"I have owned this building for 20 years and have had no issues at all with the pipes or plumbing, so I was shocked when something like this happened," Watts said.
Watts said after initiating his own investigation with a drain camera and telling Powell what was happening with the broken pipe on city property, he was still offered no assistance until he dug a hole in front of his building and installed a clean out for city crews to inspect.
Watts said he was then forced to hire his own plumbers, who confirmed that the pipe was broken on city property. At this point, Watts inquired through email where the city wanted him to send the invoices for the needed repairs as the tenants had not been able to utilize the plumbing for several days. It was then that Watts said city crews came to excavate the dirt and replace the broken sewer line.
Powell said that city crews were dispatched once the break was confirmed and were able to repair the pipe.
"I want to commend the City Sewer employee
It was then that Watts began to request insurance information for Casey Slone's construction company from city officials, eventually receiving the information and officially filing a claim with the company for damages.
"As I'm sure you know, I didn't want to be involved with radio, newspaper or any other outspoken means; however, they continue to put you in a corner, no one wants to make waves, but their questionable behavior won't stop, and unnecessary damages continue to happen," Watts said, "Couple this with watching the mistreatment of some of my neighbors, and I realized it would only be for selfish reasons that I wouldn't say something."



CVS tumbles as Aetna faces soaring medical costs and Medicare Advantage hit
Coffelt joins FCS Financial
Advisor News
- Companies take greater interest in employee financial wellness
- Tax refund won’t do what fed says it will
- Amazon Go validates a warning to advisors
- Principal builds momentum for 2026 after a strong Q4
- Planning for a retirement that could last to age 100
More Advisor NewsAnnuity News
- Corebridge Financial powers through executive shakeup with big sales
- Half of retirees fear running out of money, MetLife finds
- Planning for a retirement that could last to age 100
- Annuity check fraud: What advisors should tell clients
- Allianz Life Launches Fixed Index Annuity Content on Interactive Tool
More Annuity NewsHealth/Employee Benefits News
- Medicare and covering clinical trial prescriptions
- Cut to GLP-1 coverage prevents personnel cuts this year, but fiscal challenges ahead for Chelmsford
- Striking nurses back bill requiring health plans that receive state subsidies to disclose investments
- Recent Studies from University of Tennessee Add New Data to COVID-19 (Uncovering Gaps in Childhood Vaccine Coverage: A Post-COVID-19 Analysis of Vaccine Disparities in Tennessee): Coronavirus – COVID-19
- Researchers from University of California Discuss Findings in COVID-19 (Assessing the Use of Medical Insurance Claims and Electronic Health Records to Measure COVID-19 Vaccination During Pregnancy): Coronavirus – COVID-19
More Health/Employee Benefits NewsLife Insurance News