EDITORIAL: Rail overbids force reappraisal
| By The Honolulu Star-Advertiser | |
| McClatchy-Tribune Information Services |
This raises alarm bells, not merely that costs are rising in an accelerating construction market but real fears that they're doing so at a pace that will burn through even the generous contingency fund set aside for such overruns.
There's enormous urgency for the
HART Executive Director
However, with about 35 percent of the project still left to contract for
"Clearly our estimates right now are suspect,"
Grabauskas said the executive office is poring through the bids to discover what factors are driving the high prices. He declined to go public with any potential cost-saving ideas, beyond saying that the bid likely relates to the size of the project: nine stations in one contract.
Additional factors include the complexity of the work required and the "compressed" schedule -- time lost in court is being recouped through an accelerated timeline, he said, a schedule that may be forcing prospective bidders to increase projections of both labor and equipment costs.
The construction calendar was shortened in an effort to make a 2017 deadline to open part of the system, roughly the first 10 miles. However, officials ought to consider pushing that off if it means significant savings can be achieved.
The Ironclad deadline for the start of operation, under the federal full-funding agreement, is
HART needs to look for other ways of setting up the contracts that would encourage more competitive bidding, given the somewhat limited availability of subcontractors for the longer term of a nine-station project. Officials need to figure whether enough savings await to warrant rebidding this project, but at the very least, restructuring the next contracts in line must be explored.
Grabauskas also said the commitment to the federal government is to budget for a
The "red-hot" construction economy that Grabauskas described may yield enhanced tax revenues for the project, but the authority can't count on that. HART should work to leave some money in the account to launch a system that's built well and with fiscal support.
If adjusting the financial planning means the trial run will have to start a year or so later, most taxpayers would see that as preferable to landing in a sea of red ink.
___
(c)2014 The Honolulu Star-Advertiser
Visit The Honolulu Star-Advertiser at www.staradvertiser.com
Distributed by MCT Information Services
| Wordcount: | 677 |



Advisor News
- Financial shocks, caregiving gaps and inflation pressures persist
- Americans unprepared for increased longevity
- More investors will seek comprehensive financial planning
- Midlife planning for women: why it matters and how advisors should adapt
- Tax anxiety is real, although few have a plan to address it
More Advisor NewsAnnuity News
- LIMRA: Annuity sales notch 10th consecutive $100B+ quarter
- AIG to sell remaining shares in Corebridge Financial
- Corebridge Financial, Equitable Holdings post Q1 earnings as merger looms
- AM Best Assigns Credit Ratings to Calix Re Limited
- Transamerica introduces new RILA with optional income features
More Annuity NewsHealth/Employee Benefits News
- LEADING HEALTH ORGANIZATIONS URGE NC LAWMAKERS TO RECONSIDER IMPLEMENTATION OF MEDICAID CUTS
- PCA PAPER WORKERS IN MINNESOTA RATIFY STRONG AGREEMENT WITH MAJOR WAGE GAINS, PROTECTED HEALTH INSURANCE
- Humana is cutting Medicare benefits for hundreds of thousands in GA. Here's who will be affected
- CMS Releases Proposed Rule To Improve Prior Authorization Processes
- Her passion is nurse safety: 'It's saving healthcare workers' lives'
More Health/Employee Benefits NewsLife Insurance News
- AM Best Assigns Credit Ratings to Tokio Marine Newa Insurance Co., Ltd.
- Earnings roundup: Prudential works to save ‘unique’ Japanese market
- How life insurance became a living-benefits strategy
- Financial Focus : Keep your beneficiary choices up to date
- Equitable-Corebridge merger casts shadow over life insurance earnings
More Life Insurance News