IT Upgrade For State Dogged By Delays
Jarosz, Francesca |
The state missed a
Nearly four years later, the effort to shift from a hodgepodge of archaic IT systems to one that automates the agency's processes for employers and those claiming unemployment benefits remains unfinished.
Meanwhile, the project's costs have almost doubled, from the original
Workforce development officials say a torrent of unemployment claims and changing federal mandates regarding unemployment insurance contributed to the delay. In addition, DWD Commissioner
"The decision was made to be more, rather than less, ambitious," said Everson, who has led the department since
A review of contract amendments for the project shows that other factors - including massive turnover among personnel assigned to the project and a shuffling of subcontractors - also played a role in the delays and cost overruns.
And the ramifications of delaying the project go beyond time and money, experts say. Because computer technology increases speed and capacity every 18 months, dragging out such a project can create a self-perpetuating cycle in which delays spark the need for additional upgrades.
"Those technology pieces become old and outdated. You can still run them, but you get to a point where they put an additional load on the system," said
Everson said he doesn't anticipate that missing the most recent completion date would add cost to the project. The contract has been amended with a completion date of
'Constant changes'
Workforce development undertook the modernization project to make the system, which handles the claims for those laid off from jobs, more accessible to users and employees.
Some of the changes under the new system include allowing unemployed residents to file for benefits through an online portal, letting employers protest claims online, and automating accounting.
Those functions are being rolled out in phases, so employees already can, for example, file for benefits online.
Once completed, all of the department's unemployment insurance functions will be tied together, which will make it the first - integrated system in the country, Everson said.
But the road to completion has been fraught with hold-ups.
The first big delay which pushed the implementation date to
A year later, a new feature designed to automate certain manual tasks was added, increasing the cost by
Experts say such additions are common in large-scale technology projects. The constant availability of additional technology makes it tempting for public- or private-sector clients to add features.
And especially in government IT projects, organization leaders are likely to underestimate the cost and time needed to complete a project.
"You try to predict the cost and resources it's going to take," said
Everson said factors outside the state's control drove the additional time and cost.
For example, over the last few years, the federal government has frequently changed mandates regarding the duration of benefits, and those changes require alterations to the system's software and testing. That adds time to the project and cost for extra manpower.
On top of that, when the economy crashed in 2008, the department's unemployment claims increased 300 percent. That required the department to upgrade its computers to accommodate the increased claim volume, taking resources away from modernization efforts.
"You don't have a static set of conditions," Everson said. "You have these constant changes that are taking place."
Contract amendments in 2009, 2010 and last summer detail legislative changes and increased system demand as factors that contributed to the delay in implementation and the need to increase the scope of the project.
Technology experts agree those factors likely played a role in the delay and cost additions. But
"In systems it's very meaningful to ask, will my usage of the system change five years from now?" Sundaram said. "It's a logical explanation for the [delay], but you wouldn't be in that situation if architectural people thought about these things the right way upfront."
Shifting personnel
Cost overruns and delays certainly aren't rare in large-scale modernization projects. A survey released in 2008 of 800 IT managers conducted by research firm Dynamic Markets found that 62 percent of IT projects ran behind schedule, and 49 percent were over budget.
But experts who weighed in on
"Seven years for an IT project is really, really long," Heller said. "
High turnover also contributed to the delay. A contract amendment from
A
Then, in
When asked whether such personnel shifts have affected the timing and cost of the project, DeMarco responded, "Unequivocally, yes."
"[Tier] had multiple people leave and turn over - this caused some challenges in getting this done," he said.
Experts say heavy turnover isn't uncommon, particularly since demand is high for software developers. But they say those changes cause delays, both because new staffers need to be brought up to speed and because many come with their own ideas about how things should be done.
In addition, turnover affects morale, which can dampen employees' enthusiasm for the project, Sundaram said.
"If the people that fully understand the vision turn over, the vision can get diluted with the next group of people that comes in," Sundaram said.
"Imagine if midway through the football season, you change a team's key players. What hopes do you have of making it to the Super Bowl?"
Copyright: | |
Source: | Proquest LLC |
Wordcount: | 1293 |
InsurCard Introduces Visa Prepaid Card for Workers Compensation Payments
Advisor News
Annuity News
Health/Employee Benefits News
Life Insurance News