Work near CTA Yellow Line raised alarm before embankment collapse
Monitoring of the CTA rails and a steel bridge revealed that vibrations, settlement and movement of the track system often exceeded the limits initially laid down by transit agency officials to safeguard Yellow Line commuters riding across the 50-foot-high dirt embankment, according to the internal emails and other documents.
The situation was further complicated by changes in the design of waste disinfection facilities that pushed construction at the Terrence J. O'Brien treatment plant even closer to the Yellow Line viaduct, according to the documents released by the
On
In the interim, Yellow Line commuters, who accounted for about 2,900 trips each weekday, have been forced to use much slower shuttle buses between
The water district still is investigating what caused the embankment to fail, though there is no question that the construction triggered the accident, officials say. How quickly and easily the embankment can be rebuilt and train service restarted isn't clear, with CTA and water district officials disagreeing on what the work entails or even when it should begin.
Safety rules altered
Several weeks before the more than 100-year-old embankment failed this spring, the water district's contractor,
By agreement, the bounce, as engineers call it, could not exceed a quarter-inch. If more movement was detected, construction operations were required to stop immediately. The CTA would then conduct inspections and decide how to proceed, documents specified.
But excessive track movement became a chronic issue when excavation for the disinfection facilities ramped up this year. In April, a month before the CTA embankment failed, survey monitoring results of the tracks some distance north of Walsh's work showed variations surpassing an inch of movement, documents show.
"The 1/4-inch tolerance will be an issue every time we take readings," Pozzi wrote in a follow-up email on the morning of
Pozzi suggested that a tripling of the safety tolerance -- to three-quarters of an inch -- be allowed under the stipulation that the CTA would be notified.
"Movements over 3/4th inch, Walsh stops work until CTA authorizes work to proceed," Pozzi proposed in the email.
About two hours later, the CTA construction oversight manager, a contract worker named
McCarthy cited "ground thawing" and a "re-baselining," or recalibrating, of survey settings as justification for the more lenient safety standard.
Then at
Walsh, which is one of the largest construction contractors in
CTA officials told the Tribune that they were confident about relaxing the rules because in addition to the normal visual inspections conducted by CTA track crews, Walsh had been using special monitoring equipment while digging was going on near the Yellow Line.
Up to two inches of track movement has been allowed in some CTA projects, said
Two independent engineers who are familiar with CTA operations said it is accepted practice to conservatively set a limiting metric for track movement based on information in hand, and then to modestly increase the limit, if necessary, to a predetermined maximum as a project proceeds and while continuing to monitor conditions below surface level.
As construction at the O'Brien wastewater treatment plant progressed last spring, excessive movement of the CTA tracks and the sloped embankment prompted construction stoppages at least two times, said
More issues pile up
In late 2014, an engineer reviewing blueprints to build the
The work covered in the change order required "additional excavation and reinforcement," according to the district. The digging and shoring up were being done on the weekend of the embankment collapse, documents show.
This design modification was worrisome to CTA officials.
"The eight-foot change brought the construction work much closer to our track. It was a concern," Harper said in an interview last week. As a result, Walsh was required to make changes in the installation of pipes for the disinfection facilities, including doing some of the work during overnight hours when the Yellow Line was not running, he said.
How to rebuild
With just about two months before the promised reopening of the Yellow Line, decisions about how to rebuild the embankment are on hold, CTA officials said. The fix must be based on the outcome of the water district's ongoing investigation into what caused the embankment to fail, transit officials said, emphasizing that their top priority is to prevent any possibility of a recurrence, followed next by resuming rail service as soon as possible.
"Once the cause is determined, there has to be an engineering solution," said
But the top official at the water district said the process can be expedited so that the Yellow Line reopens in October, as previously promised. Besides, it might take a year to get to the bottom of why the embankment gave way, said
"The bank restoration and track replacement are pretty straightforward and simple. You don't really need to know what caused the failure to rebuild the embankment," St. Pierre told the Tribune this week.
After the collapse, water district and CTA officials said they agreed that the most efficient and safest solution was to first complete the sanitation pipe construction, then worry about rebuilding the embankment once the cause of the collapse was known. Under an agreement between the agencies, the pipe work is scheduled to be completed in early October, St. Pierre said. In order to meet the end of October deadline, the CTA will have just a few weeks to rebuild the track, install signals and run test trains, officials said.
The emails obtained by the Tribune reveal what appears to be a lack of urgency by the public agencies and Walsh. A full month after the collapse, officials were discussing when to hold "coordination meetings" on how to begin cleaning up the embankment landslide. The MWRD said 19 emails related to the embankment collapse were exempt from disclosure to the Tribune under the Freedom of Information Act.
CTA, riders both lose
The CTA is tallying losses related to the Yellow Line shutdown and the accident investigation. The cost through the end of June is
The revenue drop-off includes a range of categories, from lost fares and free shuttle bus service, to uncollected parking fees at the
No lawsuits have been filed to date, but some experts said litigation is inevitable. St. Pierre said insurance will protect the water district and taxpayers.
The district has not publicly disclosed the cost of the accident.
"We don't believe it will be the district's (insurance policy) deductible," St. Pierre said. "It will be someone else's deductible, whether Walsh or someone else."
Retired college professor
Graddy, 71, said he is concerned that Yellow Line riders will abandon the service and that the CTA might respond by doing something drastic, like eliminating weekend service.
Asked whether Yellow Line customers should count on service resuming in October, CTA President
The CTA examined whether it would be possible to temporarily repair the embankment and tracks to restore Yellow Line service while permanent fixes were made, and agency officials decided that "none of the concepts offered more than a marginal time savings," said CTA spokesman
But the projected five-month shutdown of the Yellow Line seems excessive to some transportation experts, who said there is no technological reason that a temporary bridge could not be built to run trains while a permanent fix is designed and built.
"Could they do a temporary restoration (of the embankment)? It is hard for me to imagine that they couldn't. They replaced much longer bridges in
Schofer said the monthslong service interruption will make it difficult for the CTA to win back the 2,600 rider trips that the Yellow Line provided on an average weekday.
"Nobody wants to beat up on CTA," Schofer said. "But someone goofed, and the slow restoration compounds the error."
___
(c)2015 the Chicago Tribune
Visit the Chicago Tribune at www.chicagotribune.com
Distributed by Tribune Content Agency, LLC.



Advisor News
- Take advantage of the exploding $800B IRA rollover market
- Study finds more households move investable assets across firms
- Could workplace benefits help solve America’s long-term care gap?
- The best way to use a tax refund? Create a holistic plan
- CFP Board appoints K. Dane Snowden as CEO
More Advisor NewsAnnuity News
- $80k surrender charge at stake as Navy vet, Ameritas do battle in court
- Sammons Institutional Group® Launches Summit LadderedSM
- Protective Expands Life & Annuity Distribution with Alfa Insurance
- Annuities: A key tool in battling inflation
- Pinnacle Financial Services Launches New Agent Website, Elevating the Digital Experience for Independent Agents Nationwide
More Annuity NewsHealth/Employee Benefits News
- Idaho is among the most expensive states to give birth in. Here are the rankings
- Some farmers take hard hit on health insurance costs
Farmers now owe a lot more for health insurance (copy)
- Providers fear illness uptick
- JAN. 30, 2026: NATIONAL ADVOCACY UPDATE
- Advocates for elderly target utility, insurance costs
More Health/Employee Benefits NewsLife Insurance News
- AM Best Affirms Credit Ratings of Etiqa General Insurance Berhad
- Life insurance application activity hits record growth in 2025, MIB reports
- AM Best Revises Outlooks to Positive for Well Link Life Insurance Company Limited
- Investors holding $130M in PHL benefits slam liquidation, seek to intervene
- Elevance making difficult decisions amid healthcare minefield
More Life Insurance News