I-4 Ultimate: Delays, overruns and deaths plague project
Today, the 21-mile and
Some of the issues:
-- The fifth death of a construction worker last month that preliminary findings say would have been avoidable with a more cautious approach to bridge building that SGL Constructors made mandatory this month.
-- Construction consortium
-- Claims for damage to vehicles and property from construction reaching almost 1,000. Nearly three-quarters have gotten no payment; a previous examination by the
-- State officials remaining silent for more than a year on the status of a bill for
-- The scaling back this summer of a signature feature for I-4 Ultimate from an artistically soaring, curving bridge for cycling and walking over the interstate in
"The construction process is now more than an inconvenience, it is endangering the lives of commuters, workers and visitors," said
The I-4 Ultimate
With its investment,
Countless drivers can't wait until the work is done, having had enough already of white-knuckle driving.
"Each time that I go on I-4, I'm praying that whoever is driving around me is familiar with the road and understands that the lanes are going to change suddenly. Even then I am unsure because how it was yesterday may not be how it is today," said
"I do everything I can to avoid I-4 if possible by leaving very early and taking alternate routes. But since the construction has gotten worse, there's a lot more traffic on the back roads. It feels as if everyone has the same idea to avoid I-4," Brown-Hayes said.
The project spans from north of
Payments to
Where I-4 Mobility Partner's claim against the state for an additional
"This project has been very challenging as you can imagine," said
"Just the pure escalation of costs and uncertainty of future pricing greatly outweigh the current disputes on the project," Prasad said. "Would you rather have this 20 miles done in one shot or subject commuters to the never-ending sight of orange barrels for decades."
Florida DOT officials have agreed to brief MetroPlan Orlando, the region's transportation planning agency with a board of local mayors and council members. Set for December, the presentation is to cover schedule and finances for I-4 Ultimate.
With the number of days over schedule continuing to climb, the department of transportation announced this summer that the proposed, showcase
But, in general, he said, a potential downside of a public-private partnership is that a contractor or developer, when taking on myriad risks and conditions of a big job, and then confronted with setbacks, may "start to search for ways to cut losses: this situation, however, could lead to unwanted actions like changing means and methods, reducing material quality, etc."
That, in laymen's terms, Garvin said, frequently means "cutting corners."
"While transferring risks from the public to the private sector may appear to be advantageous at the outset, this can backfire, particularly if the private developer has limited means to manage or control the risks," Garvin said.
Not widely known is that the price of I-4 Ultimate includes an estimated
Beginning this year, according to original project terms, the Florida DOT is scheduled to divert millions of dollars each year from state road projects in
Original projections put the amounts at
MetroPlan Orlando in 2013 implored state transportation officials to avoid diverting that money from local road improvements.
FDOT officials did not response to a request for an explanation of whether it will subtract
Perhaps tied to budget and schedule troubles, SGL Constructors, comprised of high-profile road builders, has had repeated failures with a core competency and essential responsibility: keeping workers alive.
The credit rating company noted the consortium already has accelerated construction work, but is experiencing above-average turnover of employees, "some of which have limited construction experience."
Documents disclosed by the department of transportation contain revealing details about a routine installation of a bridge beam, or girder, that turned disastrous on
Worker
The girder picked up by a crane from a truck that Saturday night was garden-variety compared with others in the vicinity where it was to be permanently affixed: the intersection of
The intersection's assemblage of bridges and ramps will rise to 120 feet; far below is bridge 246/226 as identified by investigators, where the accident occurred.
Beneath bridge 246/226 is bare ground, rather than another bridge or traffic lane that would have markedly stepped up the complexity of the installation.
After the accident, Florida DOT officials released two documents: a memorandum of preliminary accident findings and a "Girder Erection Plan" for a bridge near where the accident occurred.
What happened, according to the memo by the international engineering firm of
The memo states that SGL specifications allows for crane release before the girder is braced into place.
"For a short period of time the girder is unbraced, supported solely on the bearing pad," the memo states. "Unfortunately, the girder in question overturned/slid." There is no memo reference to what moved the girder.
Gouges visible in the concrete substructures of the bridge indicate the girder, once it was rolled onto its side, buckled and collapsed to the ground, killing Ibarra.
According to construction experts, girders are extremely strong in an upright position but cannot support their own weight when turned sideways.
SGL announced three days after the
The Girder Erection Plan released by DOT was for a bridge at
SGL Constructors did not respond when asked if procedures were violated in the fatal incident installation.
Florida DOT officials did not comply with a request for a record of fatalities on its road projects, answering that such records were the responsibility of the
The record of five fatalities on I-4 Ultimate is a grim outlier compared to other very large, contemporary road projects done by leading contractors in
The
The expressway authority has recorded two worker deaths in its history, both involving drunk drivers, but none from a construction accident.
The six-year project was finished on time in 2014 meeting its budget of
___
(c)2019 The Orlando Sentinel (Orlando, Fla.)
Visit The Orlando Sentinel (Orlando, Fla.) at www.OrlandoSentinel.com
Distributed by Tribune Content Agency, LLC.


‘Bucksport is an island’: Can flooding in Bucksport be fixed through new flood plan?
Seeman Holtz Property & Casualty Continues Its Rapid Expansion Up the Atlantic Coast
Advisor News
- I started using AI, but what now?
- How to support an entrepreneur client with multiple businesses
- Could a narrower focus help grow your practice?
- U.S. debt hits $40 trillion: how to support concerned clients
- Flourish brings private-bank-like cash solution to MassMutual’s network
More Advisor NewsAnnuity News
- MassMutual Expands Lending Options With New Secured Credit Line
- Corebridge Financial Introduces Progressive Trigger, a First-of-Its-Kind Index Annuity Strategy Designed to Turn Missed Years into Future Opportunity
- Insurer proposes $1.1M deal to resolve CA teachers’ annuity fee lawsuit
- IMOs get frustrated with slow carrier adoption of faster technology
- New class-action lawsuit targets Delaware Life over annuity disclosures
More Annuity NewsHealth/Employee Benefits News
- Minnesota seniors face tough choices for health plans
- Recent Findings from New York University (NYU) Langone Health Provide New Insights into Managed Care (State Medicaid Body Mass Index Requirements for Solid Organ Transplant Coverage: A 50-State Policy Review): Managed Care
- After booting 760K off ACA health plans, the Trump administration adds some people back
- New Findings from University of Hawaii at Manoa in the Area of Science Reported (Expanded Medi-Cal Coverage and Persisting Access Barriers for Latino Immigrants in California): Science
- What’s shaping retirement readiness in healthcare?
More Health/Employee Benefits NewsLife Insurance News