The greatest challenges in TBM tunneling: Experiences from the field
By Chorley, Steve | |
Proquest LLC |
Tunnel boring machine (TBM) tunneling is an everincreasing prospect for underground construction, and, with each new tunnel bored, there are unknown elements. When boring through the earth, even extensive geotechnical baseline reports can miss fault lines, water inflows, squeezing ground, rock bursting and other types of extreme conditions. This article draws on the considerable field service experience within Robbins to analyze successful methods of dealing with the most challenging conditions encountered.
Many tunnel projects are located in areas with relatively poor access along the tunnel alignment and bored under extremely high overburden.These two factors often result in limited geological information. It would be reason__able to state that the deeper the tunnel, the greater the level of uncertainties. When faced with these uncertainties everyone involved with the project ineluding the owner, the contractor and the machine supplier must be prepared to tackle geological surprises. This article describes the problematic geological conditions and associated difficulties faced on three separate projects and the measures that were taken to overcome these difficulties.
Kargi Kizilirmak hydroelectric project
The Kargi Kizilirmak hydroelectric project is located on the
Issues encountered (trapped cutterhead). The machine was launched in the spring of 2012 and almost immediately encountered geology that was substantially more problematic than was described in the geological reports. The geology consisted of blocky rock, sand and clays. As a countermeasure that was immediately put into place to avoid the cutterhead becoming stuck in the blocky material, crews began boring half strokes and half resets. This ensured that there was always the option of rapidly retracting the cutterhead in the event that torque reached critical levels. After boring through 80 m (262 ft) of these difficult ground conditions, the machine encountered a section of extremely loose running ground with high clay content. A collapse occurred in front of the cutterhead and the cathedral effect resulted in a cavity forming that extended more than 10 m (32 ft) above the crown of the tunnel. The weight of the collapsed material trapped the cutterhead. After several unsuccessful attempts to clean out and restart the cutterhead, consolidation of the ground above and in front of the machine was carried out. Injection of polyurethane resins via lances inserted through the cutter housings and muck buckets was the method utilized for consolidation operations.
However, injection locations were restricted to the available openings and subsequent attempts to restart the cutterhead proved to be unsuccessful.
Bypass tunnel. After assessing all of the available options, it was decided that a bypass tunnel would be required. Robbins field service assisted Gülermak with bypass tunnel design and work procedures to free the cutterhead and stabilize the disturbed ground. Blasting techniques were ruled out due to concern over further collapses caused by blast induced vibration. Hence, the excavation was undertaken using pneumatic hand held breakers. Details of the bypass tunnel can be seen in Figs. 2 and 3.
Upon completion of the bypass tunnel, further stabilization of the collapsed material above the machine and the ground ahead of the machine was carried out. The injection process this time was far more comprehensive due to the vastly improved access provided by the bypass tunnel. The area around the cutterhead was able to be cleared of material and the cutterhead was freed, allowing boring to recommence.
At this point, it was believed that the collapse was an isolated event and that the geology would improve as the overburden increased.
However, material for a second bypass tunnel was stored at the site. Unfortunately, this measure proved to be prudent planning. Although the machine passed through several weak zones successfully, a further five bypass tunnels were required to free the cutterhead during the first 2 km (1.2 miles) of boring. Robbins and Gülermak analyzed the bypass tunnel excavation procedures and implemented improvements that resulted in a reduction in the time taken for bypass operations from 28 days to 14 days. One of the main aspects of the improved procedures was the implementation of breaking out for the bypass tunnel through the telescopic shield area of theTBM rather than the accepted norm of breaking out from the tail shield. This modification resulted in reducing the length of each bypass tunnel by more than 4 m (13 ft).
Pipe roof canopy. The possibility of installing ground support such as fore-poles or a pipe roof canopy ahead of the tunnel face was investigated and, after consultation with Gülermak, a custom design canopy drill was installed in the forward shield for installation of a tube canopy (Figs. 4 and 5). The space in the forward shield area is limited. Hence, the extension section of each tube is only 1 m (3.2 ft) in length. However, the advantages of drilling closer to the tunnel face more than compensates for the time spent adding extensions to the tube length. The location of the canopy drill reduces the length of each canopy tube by more than 3 m (10 ft) when compared to installation using the main TBM probe drills. Apart from the obvious savings in drilling time, the extra 3 m (10 ft) of drilling length can result in a significant increase in hole deviation.The diameter of the canopy tubes is 90 mm (3.5 in.), each canopy typically extends up to 10 m (33 ft) from the tunnel face and the drill positioner, carriage and slew ring provide 130° of coverage.
Squeezing ground. The time dependency of ground behavior is due to the creep and consolidation processes taking place around the tunnel (Anagnostou & Kovári, 2005). In many cases, the convergence can be a gradual process taking place over a period of days, weeks or even months. On several stretches of the Kargi Tbnnel, rapid convergences occurred in the space of a few hours. The geology at the time of these rapid convergences consisted of Serpentine with high content of swelling clay. The convergence was of a radial nature, and distributed relatively evenly around the profile of the TBM.
Probe drilling ahead of the tunnel face identified the majority of the areas considered to be at risk from squeezing conditions. As it is generally accepted that there is a direct relationship between TBM advance rates and problems caused by squeezing ground, it was essential that TBM downtime was minimized while boring through these stretches. On the occasions that squeezing ground had been identified, all outstanding maintenance works, repairs and replacement of worn cutters was completed before boring through the zone of concern commenced. Inevitably, even after taking these precautions, there were unscheduled stoppages. On many occasions, the only successful means of restarting the machine after stoppages in convergence zones was to utilize single shield mode boring. In this mode, the TBM gripper shoes are retracted, the main thrust cylinders are closed up and the auxiliary thrust cylinders are utilized to propel the machine forward by thrusting off the segmental lining. The typical thrust force for standard boring operations using the main thrust cylinders on the Kargi machine is approximately 21,000 kN. On several occasions, thrust force up to 136,000 kN was applied through the auxiliary thrust system before the machine could be freed from squeezing ground. Generally after boring 1 - 2 m (3.3 - 6.6 ft) in single shield mode, the TBM was freed and it was possible to return to double shield mode.
On several stretches of tunnel, the rate of convergence, coupled with the comparative softness of the ground, caused the gripper shield to act as a plough and force muck into the telescopic shield area. The buildup of material became so severe that a mucking system had to be installed in the telescopic shield area.The system consisted of two electric hoists mounted on a running beam that allowed muck kibbles to be placed, lifted, and emptied directly onto the TBM conveyor.
Another measure used to combat the effects of the squeezing ground was the application of a polymer-based, biodegradable lubricant to the extrados of the TBM shields. Eight injection ports were installed around the perimeter of the forward shield and lubrication was injected when boring through convergence zones. It is difficult to quantify the advantage obtained as there was very little consistency in ground conditions and associated thrust pressures. However, it is clear that the application of lubrication reduced the frictional forces between the shields and converging ground.
Solution (gear reduction).To further mitigate the effects of squeezing ground or collapses, custom-made gear reducers were ordered and retrofitted to the cutterhead motors as a solution.They were installed between the drive motor and the primary two-stage planetary gearboxes. During standard boring operations, the gear reducers operate at a ratio of 1:1, offering no additional reduction and allowing the cutterhead to reach design speeds for hard rock boring. When the machine encounters loose or squeezing ground, the reducers are engaged, which results in a reduction in cutterhead speed but the available torque is increased. Figure 6 shows the torque curves for both standard and reduced gearing.
Since the installation of the canopy drill and the increase in available cutterhead torque, the TBM has traversed several sections of adverse geology including stretches of severe convergence without becoming trapped. As of
Los Olmos
The machine was launched in
The procedures for installation of the
1. Two slats, formed from 6 mm (0.2 in.) rebar, are loaded into each of the pockets.
2. The upper slats in each pocket are drawn from the pocket and pinned to the tunnel wall by means of ring beams or rock bolts.
3. As the machine advances, the slats are held in place and extruded from the pockets.
4. When the leading edge of the upper slat is completely withdrawn, it is fixed to the trailing edge of the lower slat, with an overlap of 200 mm (7.8 in.). Additional slats are then loaded.
The main advantage of the
Incorporation of the
Parbati hydro electric project stage II
The Parbati hydroelectric project stage II is located in the Kullu district of
The contractor, Himachal joint venture (HJV), purchased a refurbished Robbins-Atlas Jarva TBM from Norwegian company NCC.The machine was launched in
Rock bursts. By
Probe drilling. The Parbati project is typical of many hydroelectric projects in that it is located in a mountainous area where there is limited access and high overburden above the alignment of the tunnel. These factors resulted in limited availability of detailed geological information. Bearing this in mind, geological investigation ahead of the tunnel face was essential and was achieved by maintaining a strict regime of probe drilling.
A routine probe hole (PI ) was drilled at chaînage 4,056 m (13,307 ft) at the 11 o'clock position on the face. The depth of the hole was 27 m (88.5 ft) and minor ingress of water and silt was observed from probe chaînage 4,066.5 m (13,341 ft) up to 4,077.3 m (13,376 ft). A decision was made to drill a second probe hole (P2) at the 1 o'clock face position in order to gain further information on the geology/hydrology ahead of the face. During the night shift of
Inundation. Due to the high pressure and high volume of the discharge, it was decided that the best course of action would be to drill drainage holes to relieve the pressure ahead of the tunnel face, before consolidation grouting could be undertaken. Both drainage holes and grout holes were to be drilled via standpipes.The design of the standpipe arrangement consisted of drilling a 75-mm (3-in.) hole 5 m (16 ft) deep, inserting a 6-m- (20-ft-) long, 64-mm (2.5-in.) steel pipe with a threaded section on the trailing end, and anchoring the pipe in place by cement grouting. A ball valve and pressure gauge were attached to the threaded end of the pipe.
A third probe hole (P3) was drilled, utilizing the standpipe arrangement, to a depth of 38 m (125 ft). Although the location of the P3 probe hole was adjacent to the PI probe hole location at the 10 o'clock face position, it did not encounter silt or high-pressure water. TTie next course of action was to attempt drilling a fourth hole that would intersect probe hole PI to facilitate drainage operations. The hole was drilled though a standpipe, which was subsequently fitted with a valve to enable regulation of flow, a pressure gauge and a length of 75 mm (3 in.) hose to allow drainage of material directly into the tunnel muck cars (Fig. 8).
On
On
TBM refurbishment and modification. Robbins was awarded a refurbishment contract for the TBM, as many parts and assemblies had been damaged due to being submerged for a prolonged period of time. Once the refurbishment was complete, cement grouting with OPC was carried out to consolidate the ground in front of theTBM. The project was then held up due to contractual issues until
After the modifications were completed, further consolidation grouting was carried out before the machine advanced. A system of boring in increments of 8 m (26 ft) advances, interspersed by extensive consolidation grouting, proved to be successful and the machine successfully crossed the geological feature that had caused the inundation. 50 m (164 ft) of boring was completed before the project was again held up due to contractual issues. The project was retendered early 2013 and work resumed in
Conclusions
TBMs are often the only viable option for the excavation of long tunnels with high overburden due to the impracticalities of opening several faces via adits to enable the application of traditional tunneling methods. As with the three case studies outlined in this article, geological surprises are frequently encountered in long and deep tunnels. Due to cost constraints, contractors often decide to procure a TBM that is suited to the geological baseline reports rather than opting for additional features that ensure against geological anomalies. It is more often than not possible to retrofit additional features, but TBM down time for preparatory works, installation, and component lead times is usually substantial. The actual cost of the additional features applied to the machines described in this paper would have been a fraction of the costs involved had they been installed during the manufacturing process. When compared to the overall cost of a project, additional features installed during manufacturing become almost insignificant.
Technical features on theTBM are not the only insurance required when faced with geological uncertainties. The contractor should have an action plan in place to cover all eventualities. Ground treatment materials and equipment, as well as bypass tunnel materials and equipment should be available at site. Again, the cost of these items is almost insignificant when compared to the cost of the project, and their availability will provide substantial reductions in project delays should they be required. *
(References are available from the authors.)
Copyright: | (c) 2014 Society for Mining, Metallurgy, and Exploration, Inc. |
Wordcount: | 3836 |
Henry Krumb Lecture Series SME announces the 2014-2015
Losing the veil of confidentiality
Advisor News
Annuity News
Health/Employee Benefits News
Life Insurance News