Presolicitation Notice – C– Architect/Engineering Design Services Construct New Mental Health Facility Carl Vinson VAMC Minor Project #557-380
| Federal Information & News Dispatch, Inc. |
Notice Type: Presolicitation Notice
Posted Date:
Office Address:
Subject: C-- Architect/Engineering Design Services Construct New Mental Health Facility Carl Vinson VAMC Minor Project #557-380
Classification Code: C - Architect and engineering services
Solicitation Number: VA24714R0106
Contact: Yvonne DemorestContract Specialist 478-277-2709 mailto:yvonne.demorest@va.gov [Contract Specialist's email address]
Setaside: Service-Disabled Veteran-Owned Small BusinessService-Disabled Veteran-Owned Small Business
Place of Performance (address): Carl Vinson VAMC;
Place of Performance (zipcode): 31021
Place of Performance Country:
Description:
Dublin VAMC
Architect-Engineer (A/E) Design Services
DESCRIPTION: This is a Pre-Solicitation Notice for the following services under project number 557-380.
THIS ACQUISITION IS 100% SET ASIDE FOR SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) CONCERNS.
THIS ANNOUNCEMENT IS NOT A REQUEST FOR PROPOSAL; NO SOLICITATION PACKAGE WILL BE ISSUED UNTIL AFTER AN EVALUATION HAS BEEN MADE ON THE PROVIDED SF-330.
The award of a firm fixed-price contract is anticipated. The NAICS Code for this acquisition is 541310. The applicable Small Business Size Standard is
Interested parties shall ensure current
ALL APPLICABLE CODES AND REGULATIONS APPLY.
THE SF-330 CAN BE DOWNLOADED THROUGH THE GSA FORMS LIBRARY AT: http://www.gsa.gov/portal/forms/type/TOP, type in SF330 in the "Find a Form" block and click on search.
INTERESTED FIRMS SHOULD SUBMIT THEIR CURRENT SF-330 TO:
Hand Delivered or Mail/Ship Delivery
Carl Vinson VAMC
Attention:
OR
Electronic Submission to: yvonne.demorest@va.gov.
The SF-330s are due on
The Carl Vinson VAMC,
The project shall be designed to attempt to achieve an energy consumption level that is at least 30% below the level achieved under ASHRAE Standard 90.1-2004 ( if life-cycle cost effective) using Appendix G of ASHRAE Standard 90.1-2004 to document the energy savings achieved by the design. Should a 30% reduction in energy consumption savings prove to be unattainable per life-cycle cost analysis, A/E shall evaluate alternative designs at 5% successive decrements in order to identify the most energy-efficient design that is life-cycle cost effective.
All drawings and specifications shall be submitted by A/E to VA on computer disc at the completion of the project. Drawings shall be in AUTOCAD 2010 format, with an accompanying MS Word (ver. 2007) document that lists the drawing number and a description of the drawing's content in sufficient detail to identify it. Each individual Specification shall be submitted as a single MS Word version 2007 formatted document. In addition to the individual Specification submittals, an overall document that compiles all Specifications into one, single-spaced document is also required. One additional disk containing electronic copies of all drawings in portable document format (.pdf) shall be submitted for the Contracting Officer's use. Project shall be designed to meet the prescribed VA Construction Budget; estimated cost range of construction for project 557-380 is between
Firms will be evaluated by the A/E Evaluation Board, scored, and ranked according to score. The three (3) most qualified firms will be invited to interview with the selection board, and will again be numerically scored. The firm with the highest score will be selected and asked to negotiate a fair and reasonable price. Those firms that do not rank in the short list will be notified of their exclusion from further competition. This requirement is being procured in accordance with The Brooks Act of 1972, Federal Acquisition Regulation 36.6 (FAR) and VA Acquisition Regulation 836.6 (VAAR).
The submitted SF-330s will be evaluated on the following criteria:
Evaluation Factors:
a. The team proposed for this project, including the background of the Project Manager, consultants, and other key personnel.
b. The proposed management plan, including the team organization during the design phase and construction phase.
c. Previous experience of the proposed team.
d. The proposed design approach for this project, including the proposed design
philosophy, anticipated problems, and potential solutions.
e. Techniques planned to control the schedule and costs, including the personnel
responsible for schedule and cost control.
f. Ten most recently bid project estimates to demonstrate estimating effectiveness.
g. The team design philosophy and method of implementing sustainable design.
h. Miscellaneous experience and capabilities in the realm of interior design,, value engineering and life cycle cost, energy conservation and new energy resources, to name a few.
i. Awards received for design excellence.
j. The type and amount of liability insurance carried in addition to any involvement in litigation during the past five years.
All questions regarding this announcement must be emailed to the contracting office at yvonne.demorest@va.gov.
Link/URL: https://www.fbo.gov/spg/VA/DuVAMC557/DuVAMC557/VA24714R0106/listing.html
| Copyright: | (c) 2013 Federal Information & News Dispatch, Inc. |
| Wordcount: | 1058 |


Combine Solicitation – DOCK SIDE USCGC DIAMOND BACK
Advisor News
- Survey: Most Americans still feel prosperous despite economic worries
- SEC settlement would require Tai Lopez, two others, to pay $6.8 million
- The Gen Z money paradox
- NAIFA applauds final SECURE 2.0 regulations
- What will Democrats in Congress do about healthcare and retirement?
More Advisor NewsAnnuity News
- AM Best Affirms Credit Ratings of Global Atlantic Financial Group Limited and Its Subsidiaries
- Best’s Market Segment Report: AM Best Maintains Stable Outlook on US Life/Annuity Insurance Segment
- AM Best Affirms Credit Ratings of Massachusetts Mutual Life Insurance Company and Its Subsidiaries
- Boomers want retirement protection, but their actions don’t match their mindset
- NAIC task force to address LTC riders
More Annuity NewsHealth/Employee Benefits News
- EXPLORING INSULIN COST-SHARING CAPS FOR PATIENTS WITH PRIVATE COVERAGE
- THE AMERICAN DIABETES ASSOCIATION FIGHTS TO MAINTAIN ACCESS TO HEALTH INSURANCE
- Grand jury accuses veteran of making false disability claims that defrauded VA
- States push short-term insurance as healthcare costs climb
- Study Findings on Managed Care Are Outlined in Reports from Massachusetts General Hospital (A RUC Rescue of Primary Care?): Managed Care
More Health/Employee Benefits NewsLife Insurance News
- FORMER PRINCE GEORGE'S COUNTY INSURANCE AGENT SENTENCED FOR FELONY INSURANCE THEFT SCHEME
- AM Best Affirms Credit Ratings of Ameriprise Financial, Inc. and Its Subsidiaries
- AM Best Takes Various Credit Rating Actions on Certain Subsidiaries of Auto-Owners Insurance Group
- AM Best Affirms Credit Ratings of Global Atlantic Financial Group Limited and Its Subsidiaries
- AM Best Downgrades Credit Ratings of CICA Life Insurance Company of America
More Life Insurance News